This schedule is an approximate guide to the stages involved in the Henry Company Homes construction process. Construction schedules will vary depending on different factors. Contact your Neighborhood Sales Manager (NSM) for a more detailed schedule for your home. Your NSM will keep you informed of any delays should they occur. We will make every effort to complete your home by the agreed upon date.

 

Preliminary

  • Start package sent to Personal Builder
  • Lot cleared as needed
  • Build up “building pad” if necessary

 

Stage #1:

  • Foundation forms set
  • Plumbing rough-in complete & inspected

 

Stage #2:

  • Commercial Grade Monolithic foundation inspected & poured

 

Stage #3:

  • Wall framing completed
  • Roof decking installed & house dried in

 

Stage #4:

  • Shingles installed
  • Windows & doors installed
  • HVAC duct work & furnace installed
  • Plumbing & electrical roughed in
  • Framing inspected by County

 

Stage #5:

  • Wall insulation installed
  • Drywall installed & taped
  • Siding and/or brick installed

 

Stage #6:

  • Walls & trim painted

 

Stage #7:

  • Cabinets installed
  • Driveway, porches & patios poured

 

Stage #8:

  • Mechanical trims completed
  • Electric trim out completed
  • Sod installed

 

Stage #9:

  • Carpet & vinyl installed
  • Rough clean of home completed
  • Drywall & paint touched up
  • Attic insulation installed

 

Stage #10:

  • Home totally completed & cleaned
  • Electric service established
  • Quality inspection by HCH Management prior to customer walk-thru