This schedule is an approximate guide to the stages involved in the Henry Company Homes construction process. Construction schedules will vary depending on different factors. Contact your Neighborhood Sales Manager (NSM) for a more detailed schedule for your home. Your NSM will keep you informed of any delays should they occur. We will make every effort to complete your home by the agreed upon date.
Preliminary
-
Start package sent to Personal Builder
-
Lot cleared as needed
-
Build up “building pad” if necessary
Stage #1:
-
Foundation forms set
-
Plumbing rough-in complete & inspected
Stage #2:
-
Commercial Grade Monolithic foundation inspected & poured
Stage #3:
-
Wall framing completed
-
Roof decking installed & house dried in
Stage #4:
-
Shingles installed
-
Windows & doors installed
-
HVAC duct work & furnace installed
-
Plumbing & electrical roughed in
-
Framing inspected by County
Stage #5:
-
Wall insulation installed
-
Drywall installed & taped
-
Siding and/or brick installed
Stage #6:
Stage #7:
-
Cabinets installed
-
Driveway, porches & patios poured
Stage #8:
-
Mechanical trims completed
-
Electric trim out completed
-
Sod installed
Stage #9:
-
Carpet & vinyl installed
-
Rough clean of home completed
-
Drywall & paint touched up
-
Attic insulation installed
Stage #10:
-
Home totally completed & cleaned
-
Electric service established
-
Quality inspection by HCH Management prior to customer walk-thru